As part of Anne Arundel County, Maryland’s efforts to meet 2017 and 2025 TMDL goals for the Chesapeake Bay watershed, the Department of Public Works (DPW) identified the potential for stormwater retrofit by identifying subwatersheds with significant impervious area draining to existing pond sites. Based on the evaluation, DPW selected the Severn Run Tributary 2 Subwatershed with a large regional public pond (BMP 341) for further evaluation. Of the over 700 acres within this subwatershed, 234 acres were impervious surface. The study documented that there are many stormwater facilities located throughout the subwatershed that already provide water quality treatment for the majority of the impervious acreage, located within the large tracts of recent development falling within the BMP Era of 1985‐2001.
To help the DPW maximize water quality and impervious acreage treatment within this subwatershed, Biohabitats and Century Engineering conducted a three-step feasibility study. The Biohabitats/Century began by documenting and field evaluating all existing stormwater facilities in the subwatershed, as well as identifying all potential water quality opportunities including both retrofits and new opportunities. In all, this included regional pond BMP 341, as well as 5 outfalls and 52 other upland BMP sites. Next, they calculated existing pollutant load reduction by regional pond BMP 341 and the upland BMPs, and evaluated potential retrofit and treatment opportunities for BMP 341. Lastly, they proposed and prioritized retrofit options for upland BMP opportunities available to meet any remaining treatment deficit.
This study included desktop and field assessment of existing conditions; documentation, mapping, and assessment of BMPs in the subwatershed for water quality treatment and major maintenance (or failing conditions); and identification and ranking of potential BMP retrofits and new BMPs such as the downstream receiving areas at unmanaged outfalls. The Biohabitats/Century team identified 14 upland BMPs as priority retrofits, and documented several BMPs requiring maintenance or retrofitting to address failed or failing conditions. The team provided preliminary computations for the existing water quality volume and impervious area treatment for the County’s use in seeking credit from MDE since none of this existing treatment has been included in their National Pollutant Discharge Elimination System Municipal Separate Stormwater Sewer Systems annual reporting to MDE. Based on study findings, a recommendation of “no retrofit and documentation only” was made as the best approach for regional pond BMP 341, due to site constraints and anticipated natural resource permit limitations.
The Biohabitats/Century team developed 10% feasibility/conceptual designs for retrofitting existing upland BMPs and creating new BMPs by retrofitting outfalls. Strategies included regenerative stormwater conveyance, stream and wetland restoration, and Environmental Site Design (ESD).
TAGS
Owner: Anne Arundel County
Bioregion: Chesapeake/Delaware Bays
Ecoregion: Chesapeake Rolling Coastal Plain
Physiographic province: Severn River-Chesapeake Bay
Watershed: Coastal Plain
Collaborators: Century Engineering