Located 25 northwest of Portland, Scappoose Bay is part of the widest floodplain reach of the upper Columbia River estuary, and a critical resource for migratory birds, anadromous salmon, and countless native plant and animal species. In the early 2000s, the Scappoose Bay Watershed Council identified a degraded five-mile stretch of South Scappoose Creek, one of the Bay’s major tributaries, as a priority for restoration.
As part of a long-term, multi-project restoration strategy developed by Waterways Consulting, Biohabitats Construction restored habitat quality and complexity to 0.2 miles of South Scappoose Creek. To address key limiting factors for salmonids, the Biohabitats Construction stream team completed lay-back along significant portions of the creek’s west bank, built floodplain benches at three locations along the west bank of the main channel, and installed bank log structures in a city parcel. Biohabitats also restored disturbed areas by preparing ground and applying seed and straw-mulch.
In total, the project required 4,670 CY of excavation and the installation of 10 floodplain log structures. Extra care was taken to delineate the .5 AC work site, which was accessed through Scappoose Veteran’s Park, from the public and keep construction activities separated and safe. The Scappoose Bay Watershed Council conducted post-construction planting to encourage the recolonization of native vegetation along the creek’s banks.
TAGS
Owner: Scappoose Bay Watershed Council
Bioregion: Cascadia
Ecoregion: Portland/Vancouver Basin
Physiographic province: Pacific Border
Watershed: Multnomah Channel
Collaborators: Waterways Consulting